Free Method Statement Template (UK): Word, Excel and PDF with Worked Example
A method statement form with a step-by-step sequence table, competence and emergency sections and a briefing register.
A method statement describes how a job will be done safely, step by step. The risk assessment says what could go wrong; the method statement says what the team will actually do. Clients and principal contractors ask for one before almost any construction, maintenance or installation task. This template gives you a clean six-section format and a worked example for replacing light fittings at height.
Free to use and adapt within your organisation. No sign-up, no watermark.
What is in the template
- Scope of works box, so the limits of the job are written down
- Sequence table: each step, how it is controlled, who does it and with what
- Competence table for cards and tickets (CSCS, PASMA, IPAF and similar)
- Hazard summary cross-referenced to the risk assessment
- Permits, isolations and emergency arrangements, including rescue
- Briefing register for every operative to sign
How to fill it in
- Start from the risk assessment for the task. The method statement turns its controls into actions.
- Write the sequence in the order the work happens, including set-up, isolation and handing back.
- Name roles, not just trades, and record the training each person holds.
- State how a casualty would be reached. For work at height, 'call 999' is not a rescue plan.
- Brief the team at the workface and get every signature before work starts.
- Stop and revise if the job changes. A method statement that no longer matches the work protects nobody.
Worked example
An illustrative entry, to show the level of detail an inspector or insurer expects. The download includes this example on its own page.
| Step | What is done and how (including the control measures) | By whom | Plant, tools or equipment |
|---|---|---|---|
| 1 | Set up exclusion zone below the work area with barriers and signs | Site supervisor | Barriers, signage |
| 2 | Erect mobile tower to manufacturer's instructions; PASMA-trained operatives only; complete handover tag | Two operatives | Mobile tower, tag |
| 3 | Isolate the lighting circuit at the distribution board, lock off and prove dead | Electrician | Lock-off kit, approved voltage tester |
The legal basis
No UK regulation requires a document called a method statement. HSE says so plainly. What the law requires is a safe system of work (section 2(2)(a) of the Health and Safety at Work etc. Act 1974), a risk assessment, and, on construction projects, proper planning under the Construction (Design and Management) Regulations 2015. A method statement is the usual way to show those duties have been met for higher-risk tasks.
Some regulations do demand written plans for particular work: demolition arrangements must be recorded in writing (CDM 2015 regulation 20), lifting operations must be planned (LOLER 1998 regulation 8), and work at height must be planned and supervised (Work at Height Regulations 2005 regulation 4). Keep method statements with the project file. Many contractors hold them for at least six years, in line with contract limitation periods.
Common mistakes
- Generic statements reused from the last job. The site address changes; the access, the services and the people do too.
- Describing hazards instead of steps. That is a risk assessment written twice.
- No rescue arrangement for work at height or in confined spaces.
- Nobody signs it. An unbriefed method statement is the first thing an investigator will ask about.
FAQs
Is a method statement a legal requirement?
Not by name. The law requires safe systems of work and, in construction, proper planning under CDM 2015. A method statement is the accepted way to record that for higher-risk tasks, and most clients require one by contract.
What is the difference between a risk assessment and a method statement?
A risk assessment identifies hazards and decides on controls. A method statement sets out the sequence of work and how those controls are applied at each step.
What should a method statement include?
Scope, sequence of work, people and competence, plant and equipment, hazards and controls, permits and isolations, emergency and rescue arrangements, and a briefing record.
Who writes the method statement?
The contractor doing the work, using someone who understands the task. The supervisor who will run the job should be involved, not only an office-based adviser.