Free RAMS Template (UK): Risk Assessment and Method Statement in Word, Excel and PDF

Risk assessment, method statement and briefing register in a single RAMS pack, with a worked example.

Free RAMS Template (UK): Risk Assessment and Method Statement in Word, Excel and PDF

RAMS stands for risk assessment and method statement: the two documents a client or principal contractor asks for before you start work on their site. This template puts both in one pack with a single header, so the hazards in Part A and the steps in Part B always refer to the same job, and adds the briefing register that proves the team was told.

Free to use and adapt within your organisation. No sign-up, no watermark.

What is in the template

  • Part A, risk assessment: hazards, people at risk, controls and a likelihood by severity score
  • 5x5 risk matrix so the client can read your scores
  • Part B, method statement: numbered sequence of work with responsibilities and equipment
  • Competence, PPE, permits and emergency arrangements on one row
  • Three-way sign-off: author, contractor approval and client acceptance
  • Part C, briefing register for every operative

How to fill it in

  1. Visit the site first, or get photographs and the client's site rules. RAMS written blind get rejected.
  2. Complete Part A: one hazard per row, with the controls you will really use.
  3. Write Part B from those controls, in working order.
  4. Send it for acceptance in good time. Principal contractors commonly want RAMS several working days before the start date.
  5. Brief it on site, collect signatures in Part C and keep a copy at the workface.
  6. Revise and re-brief when the scope, access or people change. Raise the revision number each time.

Worked example

An illustrative entry, to show the level of detail an inspector or insurer expects. The download includes this example on its own page.

HazardWho might be harmed and howControl measuresLSRFurther action / by whom
Fall from height during fitting replacementOperatives: fatal or major injuryMobile tower erected by PASMA-trained staff, guardrails and toe boards, tower tag checked daily, no work from ladders2510Supervisor checks tag before each shift
Falling tools or fittingsPeople below: head injuryExclusion zone with barriers, tool lanyards, materials raised and lowered in a tool bag248
Electric shock from lighting circuitElectrician: shock, burnsIsolate at board, lock off, prove dead with approved tester before touching155

The risk assessment half is a legal requirement under regulation 3 of the Management of Health and Safety at Work Regulations 1999. The method statement half is not required by name, but it is how contractors show a safe system of work under the Health and Safety at Work etc. Act 1974 and proper planning under the Construction (Design and Management) Regulations 2015. CDM regulation 15 requires contractors to plan, manage and monitor their work so that it is carried out without risks to health or safety, and regulation 13 puts the same duty on the principal contractor for the construction phase.

HSE has repeatedly warned against paperwork for its own sake: RAMS should be proportionate to the risk and written for the people doing the job. A two-page RAMS that the team has read is better evidence than a forty-page one that they have not.

Common mistakes

  • Part A and Part B that do not match. If the assessment promises an exclusion zone, a step in the method must set it up.
  • Volume over clarity. Padding RAMS with every generic hazard hides the two that matter.
  • No revision control. Two versions on site is how the wrong method gets followed.
  • Signatures collected in the canteen. Brief at the workface, where people can see what you mean.

FAQs

What does RAMS stand for?

Risk Assessment and Method Statement. It is the combined safety document most UK clients and principal contractors require from a contractor before work starts.

Are RAMS a legal requirement?

The risk assessment is. The method statement is not required by name, but safe systems of work and construction planning are, and RAMS are the normal way to demonstrate them. Clients usually make them a contract condition.

How long should RAMS be?

As short as the risk allows. HSE asks for proportionate paperwork. For routine low-risk work two or three pages is typical; complex or high-risk work needs more detail on sequence and rescue.

How long should RAMS be kept?

There is no statutory period. Keep them with the job file; many contractors keep them for at least six years, and longer where the health and safety file for the building relies on them.

Sources

hse.gov.ukHSE: CDM 2015 duties of contractorslegislation.gov.ukConstruction (Design and Management) Regulations 2015, regulation 15

Miss a deadline, pay the fine.

One email a week. Every new rule, deadline and record-keeping change that affects you.

Logbook.co.uk is an independent UK publication edited by Jamie Dawson. Guides are checked against current UK legislation and primary sources from gov.uk, HSE, ICO, DVLA, DVSA, CAA and trade bodies. Always confirm against the underlying source before acting. Nothing on this site is legal advice.